ANSI EIA X12 Preferences

Use this dialog box to select options for the ANSI EIA X12 wizard, which lets you export project information to other applications that support Version 3040 or Version 3050 of the ANSI EIA X12 Transaction Set 839 Project Cost Reporting.

Contents

Field Description
Export wInsight extended information Select this option to instruct Cobra to export the extended data set. wInsight uses an extended data set for better analysis.
  • Selecting the Secure check box for this option while the Selected check box is cleared also selects the Secure check box for the Suppress exporting the CAM field option.
  • Selecting the Secure check box for this option while the Selected check box is selected does not affect the Secure check box for the Suppress exporting the CAM field option.
  • Clearing the Selected check box for this option while the Secure check box is cleared does not affect the Secure check box for the Suppress exporting the CAM field option.
  • Clearing the Selected check box for this option while the Secure check box is selected also selects the Secure check box for the Suppress exporting the CAM field option.
The following are exported from Cobra as extended data:
  • Control account manager
  • Hourly data
  • Future monthly budget
  • ETC
Export variance narrative data Select this option to instruct Cobra to include the variance narrative entries on the CPR Format 5 when exporting ANSI EIA X12 data.
Export CSSR data Selecting this option instructs Cobra to include the CSSR information when exporting ANSI EIA X12 data.
Suppress exporting the CAM field Select this option to instruct Cobra not to export the CAM field when exporting extended data. This option is available only if you selected the Export wInsight extended information option.
  • Selecting the Secure check box for this option also selects the Secure check box for the Export wInsight extended information option.
  • Clearing the Export wInsight extended information option also clears this option, except if this option is disabled in the EPM Security Administrator (EPM SA).
Enforce consecutive forecast periods Select this option to instruct Cobra that if the project is using weekly earned value, the exports will be summarized into monthly periods.
Use yyyymmdd dates instead of yymmdd Select this option to instruct Cobra to export the dates in yyyymmdd format.
Filter unused WBS/OBS codes Select this option to instruct Cobra to exclude WBS or OBS codes that do not contain values from the export process.
Export manpower in: This option allows you to export man power as either FTE (Full-Time Equivalent) or Hours for Format 4 reports. Selecting Hours creates a CPR4 format using the result code H-Hours on the calculation of resource.
Use alternate code for WBS This option allows you to select a number, from 1 to 9, that represents the code position on the control account code file that will be used as the WBS. Cobra exports this control account code instead of the code selected for the Control Account Key Field 1. Selecting 1 means that the first code listed as an attached code on the control account is used as the alternate WBS. Selecting 0 means that the Control Account Field 1 position is used as the WBS.
Use alternate code for OBS

This option allows you to select a number, from 1 to 9, that represents the code position on the control account code file that will be used as the OBS. Cobra exports this control account code instead of the code selected for the Control Account Key Field 2. Selecting 1 means that the first code listed as an attached code on the control account is used as the alternate OBS. Selecting 0 means that the Control Account Field 2 position is used as the OBS.

WBS Project Office code

This option allows you to select a number, from 1 to 9, that represents the code position on the Control Account Field 1 (WBS) code file. The code position selected is used to extract the Project Officer data. Selecting 1 means that the code in the first code file position on the Control Account Field 1 code file is used. Selecting 0 means that there is no code in the WBS code file that represents the Project Officer code.

OBS Project Office code

This option allows you to select a number, from 1 through 9, that represents the code position on the Control Account Field 2 (OBS) code file. The code position selected is used to extract the Project Officer data. Selecting 1 means that the code in the first code file position on the Control Account Field 2 code file is used. Selecting 0 means that there is no code in the OBS code file that represents the Project Officer code.

Selected

Selecting the Selected check box for any of the options makes the option selected by default in the process wizard where it is located.

Secure Select this check box for any of the options prevents users from changing the setting for that particular option in process wizards where these options are also located. Cobra uses this feature to secure certain options while users run processes against projects.

If this check box is selected, this option cannot be modified on the options pages of the Cobra process wizards. Select this option to ensure that all users are using the same settings when running Cobra processes.